Project tıtle: SOUTH NORTH ANTALYA TANK FARM DRENAGE TANK AND WEST TURKEY POL FACILITIES ROOF AND WIRE FENCE RESTORATION
Locatıon: ANTALYA,ESKIŞEHIR,BALIKESIR,TEKIRDAG,AFYON,BURSA,ISTANBUL,BILECIK AND IZMIT.
Clıent/Owner: MSB.INŞ.EML. VE NATO GUV.YAT.D.BŞK.LIĞI/RESTAŞ A.Ş
Start Date: 31 OCTOBER 2006
Completıon Date: 03 MAY 2008
Scope of work
1- Productıon 7000m2 70mm thick wooden carrier system and coating it with trapezoidal aluminium plates(TS 4598) has been made for roof constructions at West Turkey POL Facilities fuel pump stations.
2- Under the purpose of supporting the exhaust and silencers located in the fuel pump stations at West Turkey POL facilities 20 tones ST 37 steel constructions has been made.
3- 6 units with a capacity of 10 m3 of the existing underground Horizontal Cylindrical Fuel drainage tanks removed and the new fabrication and erection Works completed
4- Dısmantlıng of the Haramidere pump station's existing wire bridges and manufacturing of new wire fence and ihata wall in accordance with NATO type.
5- 892m3 excavation is made for the 10 m3 drainage tanks which are placed underground.
6- 140 m3 stabilized fill is made for the Field concrete base under Coverings.
7- Field pavements (C20) has been made around the drainage tanks.
8- 3 cathodic production facility constructions has been made.
9- 225 m2 Epoxy has been Coated to the Drainage tanks.
10- Hydrostatic tests are performed for the drainage tanks and pipelines.
11- 155m PE isolated PN16 DN50 pipeline restoration has been completed between the drainage tanks and the pump holes.